In ExtensionP51800050904Registered May 2023Delayed 731dExtension1 red flag

5TH Element

A others project by Pratham Varadvinayak Builders and Developers Private Limited in ANDHERI WEST, Mumbai Suburban.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
63%
cost-weighted
Declared completion
Jun 2028
delayed 731d
Units sold
34 / 84
40% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Pratham Varadvinayak Builders and Developers Private Limited · Company
Project type
Others
Land area
804 m² · Permissible built-up (FSI) 6,805 m²
Total units
84 across 1 wing
Estimated cost
₹42.2 Cr
Land ownership
Promoter is the landowner
Parking
79 four-wheeler · 0 two-wheeler
Held outside open sale
32 rehab
Application date
18 Nov 2022
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA19 of 19 proposed84
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
PRATHAMESH ASSOCIATES · R/157/LS
Structural engineer
Unisteps Consulting Private Limited
Project bank
HDFC BANK
Location

Where it sits

ANDHERI WEST, Mumbai Suburban — 400058.

Locality
ANDHERI WEST
District
Mumbai Suburban
Authority
Building Permission Cell, Greater Mumbai / MHADA
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

5TH Element: common questions

Is 5TH Element RERA registered?

Yes. 5TH Element is registered with MahaRERA under registration number P51800050904, granted on 15 May 2023. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of 5TH Element?

The developer has declared completion by June 2028 in its MahaRERA filing, revised from the original June 2026. The record shows the project running 731 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of 5TH Element?

5TH Element is developed by Pratham Varadvinayak Builders and Developers Private Limited, the promoter named in its MahaRERA registration.

Where is 5TH Element located?

5TH Element is in Andheri West, Mumbai (PIN 400058), Maharashtra, as declared in its RERA registration.

How many units does 5TH Element have, and how many are sold?

5TH Element has 84 units on its RERA registration. 37 were reported sold as of September 2026, leaving 47 unsold.

How much construction of 5TH Element is complete?

By the developer's own quarterly filing, 63% of the work is done, measured against the project's cost estimate.

Is there any litigation against 5TH Element?

No litigation is declared on 5TH Element's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.