In ExtensionP51800052448Registered Sept 2023Delayed 184dExtensionNo active red flags

101 Boulevard

A others project by H M Developers in ASHOK CHAKRAVATI ROAD KANDIVILI, Mumbai Suburban.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
95%
cost-weighted
Declared completion
Dec 2026
delayed 184d
Units sold
30 / 90
33% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
H M Developers
Project type
Others
Land area
1,396 m² · Permissible built-up (FSI) 5,148 m²
Total units
90 across 2 wings
Estimated cost
₹35 Cr
Land ownership
Promoter is the landowner
Parking
78 four-wheeler · 0 two-wheeler
Held outside open sale
32 rehab
Application date
19 Aug 2023
Buildings & units

2 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA13 of 13 proposed63
NA20 of 20 proposed27
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
HEMAL SANGHAVI · CA/2008/43433
Structural engineer
FURKHAN PETTIWALA · STR/P/157
Project bank
ICICI BANK LIMITED
Location

Where it sits

ASHOK CHAKRAVATI ROAD KANDIVILI, Mumbai Suburban — 400101.

Locality
ASHOK CHAKRAVATI ROAD KANDIVILI
District
Mumbai Suburban
Authority
P-12382/2022/(117 And Other)/R/S Ward/AKURLI-R/S/CC/1/New
Red flags

No active red flags

Absence of a flag reflects the record as filed, not an assessment of safety.

Legal & encumbrance

Litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

101 Boulevard: common questions

Is 101 Boulevard RERA registered?

Yes. 101 Boulevard is registered with MahaRERA under registration number P51800052448, granted on 8 September 2023. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of 101 Boulevard?

The developer has declared completion by December 2026 in its MahaRERA filing, revised from the original June 2026. The record shows the project running 184 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of 101 Boulevard?

101 Boulevard is developed by H M Developers, the promoter named in its MahaRERA registration.

Where is 101 Boulevard located?

101 Boulevard is in Mumbai (PIN 400101), Maharashtra, as declared in its RERA registration.

How many units does 101 Boulevard have, and how many are sold?

101 Boulevard has 90 units on its RERA registration. 30 were reported sold as of September 2026, leaving 60 unsold.

How much construction of 101 Boulevard is complete?

By the developer's own quarterly filing, 95% of the work is done, measured against the project's cost estimate.

Is there any litigation against 101 Boulevard?

No litigation is declared on 101 Boulevard's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.

RERA projects nearby