In ExtensionP52100079455Registered Mar 2025Delayed 1096dExtension1 red flag

1 Priority Rathod Business Zone

A commercial project by Shreeji Developers in Pimpale Gurav, Pune.

Data as of Oct 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Oct 2026.

Construction
20%
cost-weighted
Declared completion
Dec 2029
delayed 1096d
Units sold
0 / 23
0% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Shreeji Developers · Partnership
Project type
Commercial
Land area
1,990 m² · Permissible built-up (FSI) 8,582 m²
Total units
23 across 1 wing
Estimated cost
₹10.4 Cr
Land ownership
Promoter is the landowner
Application date
03 Feb 2025
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA8 of 8 proposed23
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Shikay Group · A19749
Structural engineer
G A Bhilare
Project bank
ICICI BANK LIMITED
Location

Where it sits

Pimpale Gurav, Pune — 411061.

Locality
Pimpale Gurav
District
Pune
Authority
Pimpri-Chinchwad Municipal Corporation
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99

1 Priority Rathod Business Zone: common questions

Is 1 Priority Rathod Business Zone RERA registered?

Yes. 1 Priority Rathod Business Zone is registered with MahaRERA under registration number P52100079455, granted on 6 March 2025. As of October 2026, the registration is active under a MahaRERA extension.

What is the possession date of 1 Priority Rathod Business Zone?

The developer has declared completion by December 2029 in its MahaRERA filing, revised from the original December 2026. The record shows the project running 1096 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of 1 Priority Rathod Business Zone?

1 Priority Rathod Business Zone is developed by Shreeji Developers, the promoter named in its MahaRERA registration.

Where is 1 Priority Rathod Business Zone located?

1 Priority Rathod Business Zone is in Pimpale Gurav, Pune (PIN 411061), Maharashtra, as declared in its RERA registration.

How many units does 1 Priority Rathod Business Zone have, and how many are sold?

1 Priority Rathod Business Zone has 23 units on its RERA registration. 0 were reported sold as of October 2026, leaving 23 unsold.

How much construction of 1 Priority Rathod Business Zone is complete?

By the developer's own quarterly filing, 20% of the work is done, measured against the project's cost estimate.

Is there any litigation against 1 Priority Rathod Business Zone?

No litigation is declared on 1 Priority Rathod Business Zone's MahaRERA record as of October 2026. A clean record reflects what was filed, not a legal title check.