Macrotech Developers Limited
18 RERA-registered projects in Maharashtra
18
projects
5,434
total units
14
delayed (avg 948d)
Developer overview
- Macrotech Developers Limited has 18 RERA-registered projects with a total of 5,434 units, of which 3,114 are sold.
- 14 projects are delayed, with an average delay of 948 days.
- 20 litigation cases on record.
- 14 projects have received extension certificates.
Track record
- In Extension
- 14
- Active
- 4
Active districts
Thane (18)
Projects
Thane Project
P51700053017 · Thane
420 units20% builtRegistered 10 Oct 2023
Upper Thane-Casa Eden
P51700034837 · Thane
444 units100% built183d delayedRegistered 28 Apr 2022
Upper Thane-IRIS Wing A
P51700034862 · Thane
138 unitsRegistered 28 Apr 2022
Lodha Bellavista - Wing B1
P51700024815 · Thane
241 units78% built944d delayedRegistered 09 Mar 2020
Lodha Bellavista - Wing B2
P51700024060 · Thane
130 units52% built944d delayedRegistered 17 Jan 2020
Lodha Amara Tower 49 and 50
P51700020157 · Thane
350 units100% built1188d delayedRegistered 29 Mar 2019
Lodha Amara Tower 44
P51700020123 · Thane
154 units28% built1004d delayedRegistered 29 Mar 2019
Lodha Amara Tower 47 and 48
P51700020151 · Thane
378 units29% built1369d delayedRegistered 29 Mar 2019
Lodha Amara -Tower 42 and 43
P51700020164 · Thane
462 units69% built1006d delayedRegistered 29 Mar 2019