Dedge Housing Development LLP

2 RERA-registered projects in Maharashtra

2
projects
216
total units
2
delayed (avg 366d)

Developer overview

  • Dedge Housing Development LLP has 2 RERA-registered projects with a total of 216 units, of which 132 are sold.
  • 2 projects are delayed, with an average delay of 366 days.
  • 2 projects have received extension certificates.

Track record

In Extension
2

Active districts

Pune (2)

Projects